Nur-Sultan is among outsiders on preparation to heating season

Date: 15:29, 23-09-2019.

Astana. September 23. KazTAG - Nur-Sultan is among lagging regions on preparation to the heating season.
"Out of planned 4989.7 km heating networks, 4933 km (99%) have been repaired. Low preparedness on repair of the heating networks is in Nur-Sultan - 73.6%, Mangistau region (91.7%), Atyrau region ( 96.8%). Out of planned 15116 km of water networks 13917 km (98.7%) have been repaired - low preparedness is in Nur-Sultan (71.6%), Aktubinsk region (83.8%), Turkestan region (89.9%), Shymkent (90.5%). As for the preparation of education objects - 10967 objects have been prepared (99.6%). There are unprepared objects in Nur-Sultan, West Kazakhstan region and Atyrau region," said Beibut Atamkulov, Minister of Industry and Infrastructural Development.
Low preparedness of health care objects is in the Atyrau, Aktubinsk, West Kazakhstan regions.

Photo source: picture from an open source